How to Get a Building Permit in Kenya: A Step-by-Step Guide for Developers and Contractors

BilaFundi · 19 Sep 2026 · 6 min read · 228 views

Getting a building permit in Kenya is one of the most critical — and most misunderstood — steps in any construction project. Whether you're putting up a residential block in Nairobi, a commercial unit in Mombasa, or a warehouse in Kisumu, you cannot legally break ground without county approval. Delays at this stage routinely push project timelines back by months and inflate costs. This guide gives you a clear, practical walkthrough of the process so you can move faster and avoid the most common pitfalls.

Who Regulates Building Approvals in Kenya?

Building permits in Kenya are issued at the county level, not nationally. Each of the 47 counties has its own planning and development control department, operating under the Physical and Land Use Planning Act (2019) and the National Construction Authority (NCA) Act. In Nairobi, the lead agency is the Nairobi City County Department of Urban Planning; in Mombasa, it's the Mombasa County Government, and so on.

The NCA itself — a national body — regulates contractors and site supervision but does not issue building permits. However, NCA registration is a prerequisite for contractors working on most formal projects, so your contractor must hold a valid NCA certificate before approval will be granted.

What Projects Require a Building Permit?

Almost every construction project above a minor threshold requires county approval. This includes:

  • New residential buildings (bungalows, maisonettes, apartments)
  • Commercial and industrial developments
  • Extensions or additions to existing structures
  • Change of use of an existing building
  • Demolition of structures above a certain size

Minor works — such as internal partitioning or small repairs that don't affect structural integrity — may be exempt, but it's always worth confirming with your county office before proceeding.

Step-by-Step: How to Get a Building Permit in Kenya

Step 1 — Engage a Registered Architect or Engineer

You cannot submit a building application yourself. Drawings must be prepared and signed by professionals registered with the Board of Registration of Architects and Quantity Surveyors (BORAQS) or the Engineers Board of Kenya (EBK), depending on the scope. Structural drawings require a registered structural engineer; architectural drawings require a registered architect. Make sure your design team is current on their annual practising certificates — expired certificates are a common reason applications are rejected at intake.

Step 2 — Obtain a Land Title and Search

Before submitting, you'll need a valid land title deed (or leasehold document) and a recent official land search from the relevant lands registry. This confirms ownership and that the land is not under any encumbrances or caveats that would block development. In counties where land is held under community or trust arrangements, additional consent documentation may be required.

Step 3 — Prepare Your Submission Package

A typical building permit application package includes:

  • Completed county application form
  • Architectural drawings (site plan, floor plans, elevations, sections) — typically four to six sets of prints
  • Structural drawings and calculations
  • Geotechnical (soil) report for multi-storey or complex structures
  • Electrical and plumbing/mechanical drawings (for commercial projects)
  • Copy of title deed and official land search
  • Certificate of incorporation or PIN certificate (for companies)
  • NCA registration certificate of the appointed contractor
  • Proof of payment of application fees

Some counties now accept digital submissions via their e-citizen portals, while others still require physical submission. Check with your specific county office, as requirements vary and are updated periodically.

Step 4 — Pay Application Fees

Fees are calculated by the county based on the gross floor area and the class of development. Residential rates differ from commercial rates, and high-rise developments attract higher charges. Fees are set by each county's Finance Act and are revised from time to time — always confirm the current schedule directly with the county planning department rather than relying on figures from a previous project.

Step 5 — Await Technical Review

Once submitted, your application goes through a multi-department technical review. In Nairobi, this typically involves urban planning, structural engineering, public health, fire, and sometimes NEMA (the National Environment Management Authority) if an Environmental Impact Assessment (EIA) is required. EIA is mandatory for projects above certain thresholds — including developments on sensitive land or those above a specified gross floor area. Factor in at least four to eight weeks for this review stage under normal conditions, though complex projects or busy periods can take longer.

Step 6 — Respond to Queries and Revisions

It's common to receive a list of technical queries or required amendments. Your design team must respond promptly and resubmit revised drawings. Slow responses at this stage are one of the main causes of permit delays — assign a clear point of contact on your team to monitor and turn around queries quickly.

Step 7 — Collect Your Approved Permit

Once approved, you'll receive a stamped set of drawings and a formal development permission letter. Keep the stamped drawings on site at all times — inspectors will ask to see them. Your permit will specify the validity period (commonly two years) and any conditions attached to the approval.

📥 Free Download

Site Compliance Checklist

The permits, notifications, inspections and records a site needs to stay compliant — structured around duties that hold in any regime.

Commencement Notice and Site Inspections

Before breaking ground, you are required to submit a commencement notice to the county and, in most cases, to the NCA. This formally notifies the authorities that construction is beginning and triggers the inspection schedule. County inspectors will visit at key stages — foundation, slab, superstructure, roofing, and finishes — and must sign off at each stage before you proceed. Skipping inspections or failing to notify the county can result in stop-work orders or, in serious cases, demolition notices.

Occupation Certificate

Once construction is complete, you cannot legally occupy or let the building without an occupation certificate (sometimes called a certificate of completion). This is issued after a final inspection confirms the building was constructed in accordance with the approved drawings and relevant standards. For commercial and institutional buildings, additional sign-offs from the fire authority and public health department are typically required before the occupation certificate is granted.

Common Mistakes That Delay Permits

  • Submitting drawings signed by professionals with lapsed registration
  • Missing documents — especially the land search or NCA contractor certificate
  • Designs that don't comply with the county's zoning regulations or plot coverage limits
  • Failing to get an EIA licence where one is required before permit submission
  • Not following up regularly — applications can stall without a proactive applicant

Working With the Right Team

The single most effective way to speed up your building permit process is to engage professionals who have recent, direct experience submitting to your specific county. An architect or project manager who knows the local planning department, understands the current submission requirements, and has existing relationships with inspectors will navigate the process far more efficiently than someone working in that county for the first time.

If you're sourcing a design team or contractor for a project in Kenya, browse verified construction professionals on BilaFundi — you can filter by location, trade, and project type to find providers with relevant county experience.

Quick Reference: Kenya Building Permit Process

  • Regulating authority: County government planning department
  • Key legislation: Physical and Land Use Planning Act (2019), NCA Act
  • Who can sign drawings: BORAQS-registered architects; EBK-registered engineers
  • Contractor requirement: Valid NCA registration certificate
  • EIA requirement: Required for projects above specified thresholds — check with NEMA
  • Typical review period: 4–8 weeks (simple projects); longer for complex or multi-storey
  • Permit validity: Commonly two years from date of issue
  • Final step: Occupation certificate before use or letting
B
Written by
BilaFundi
BilaFundi Team
More articles
Comments
0
No comments yet. Start the conversation below.
Join the conversation
Sign in to leave a comment. It only takes a moment.
DON'T STOP HERE
Keep Reading
All articles →